"Together with the right of public use and access." Those words come from the standard easement the U.S. Army Corps of Engineers uses for beach projects on Gasparilla Island. They tie the most private addresses on the island to the most public question on it, which is where people park.
Through most of Boca Grande's Gulf front, the sand between a home's dune and the water has been placed and replaced by government projects on a regular schedule. The money depends on how easily the public can get to that beach. Funding, easements and parking are part of an argument that is still going on at the Lee County Commission this fall.
The Clause That Comes With the Sand
The federal Lee County Shore Protection Project places sand on private land through what the Corps calls a "Perpetual Beach Storm Damage Reduction Easement." The Corps' 2018 real estate plan for the Gasparilla Island segment describes it as perpetual and assignable. It lets the project sponsor and its contractors "construct; preserve; patrol; operate; maintain; repair; rehabilitate; and replace; a public beach," deposit sand, change contours, build berms and dunes, and "nourish and renourish periodically," all "together with the right of public use and access."
That same 2018 plan counted 196 parcels landward of the erosion control line inside the project boundary. Lee County, the local sponsor, had certified easements on 117 privately owned parcels, 44 commercially owned parcels and 19 vacant public parcels. It was still working on the remaining 16 privately owned parcels. Those counts are eight years old. They still show the basic setup. Most of the Gulf front in the project area has signed on, and a small group of parcels has historically not.
Where the Federal Line Runs
The federal project covers a defined stretch. Florida's Department of Environmental Protection places it between state monuments R10 and R24.5. Lee County described the same reach to the Boca Beacon in April 2025 as running "from 17th Street down to approximately South Beach Bar & Grille." South of that, the shoreline at Gasparilla Island State Park has its own state-run program on its own schedule.
This reach has been rebuilt many times. DEP's August 2026 Strategic Beach Management Plan for the Southwest Gulf Coast lists the history, and the Boca Beacon reported the county's costs for the earlier rounds.
| Completed | Sand placed | Location | Reported cost |
|---|---|---|---|
| April 2007 | 1,072,781 cubic yards | R10 to R26 | $11.8 million |
| December 2013 | 433,424 cubic yards | R10 to R24.5 | $7.3 million |
| June 2019 | 141,972 cubic yards | R10.2 to R15.3 | $6.5 million for the Lee County project |
| June 2019 | 139,666 cubic yards | R24 to R26.5, State Park | Not reported separately |
| April 2025 | About 150,000 cubic yards | R25 to R26.5, State Park | Not reported |
| 2026/2027, planned | About 300,000 cubic yards | R10 to R24.5 | Pending |
That is roughly one major event every six years in the federal reach. Each one costs millions, and each one depends on the easements above. The beach in front of these homes is maintained by public projects, and it needs that maintenance.
Why a Parking Space Is Worth Sand
The funding formula makes the link between parking and sand direct. The Corps told the Boca Beacon in April 2025 that its usual coastal cost share is 65 percent federal and 35 percent non-federal. That share "can be adjusted accordingly based on shoreline ownership and use and whether there is reasonable access and parking." For the maximum share, public access to a federally authorized beach should come roughly every half mile.
The state uses its own measure. According to Lee County, as reported in the same article, full state funding requires 100 parking spaces per mile of beach, or about one space for every 52.8 feet of shoreline. Credits are available for bus stops, bicycle racks and certain hotel or motel rooms. Florida law ties state cost share to "adequate public access" under section 161.101(12), Florida Statutes, as the Boca Beacon reported in July 2025.
Public access and parking are part of the debate over the public share of the bill.
What the 2025 Ordinance Put in Play
The Lee County Commission passed the Boca Grande parking ordinance on Aug. 5, 2025. Shortly before the vote, the Boca Beacon obtained an internal county email from July 2, 2025, sent by the Natural Resources Division. It said renourishment funding would need to be supplemented if the plan passed and beach access streets north of 1st Street were closed. It raised the idea of a Municipal Services Taxing or Benefit Unit on Boca Grande. It also warned that "If the parking used to calculate the FDEP percentage changes, FDEP can recalculate a new percentage and request a refund of their portion." The Beacon later reported that the email described a possible $4.2 million shortfall as one sample scenario.
At the Aug. 5, 2025 meeting, as the Boca Beacon reported, County Manager Dave Harner said the formula "could change based on this, but it doesn't mean we're not going to get state or federal dollars." Asked whether an island fee could be imposed or would need residents' approval, he said, "It's at the board's discretion." The same report said that, as of August 2025, renourishment on Gasparilla Island was fully covered by federal and state aid and Tourism Development Tax money. County spokesperson Betsy Clayton said staff would analyze the amended ordinance when federal and state partners were ready to contribute to the next project.
As of this fall, no recalculated cost share and no adopted Boca Grande renourishment assessment have appeared in public reporting. At the Oct. 6, 2026 county commission meeting, commissioners took up a proposed clarification to the ordinance's Gilchrist Avenue section. Chairman Cecil Pendergrass asked whether the county would "deal with the FEMA with the Army Corps and all the funding" at a later date, according to the Boca Beacon. At the same meeting, the board agreed to Charlotte County's request for a six-month extension of the two counties' conflict-resolution process over the ordinance.
November's Sand, and What Held It Up
DEP's August 2026 plan says the Corps is expected to use Flood Control and Coastal Emergencies funds to build the next nourishment in November 2026. It would place about 300,000 cubic yards of sand between R10 and R24.5. The plan's own project table lists the timing as "2026/2027" and calls the volume approximate. Lee County told the Boca Beacon in 2025 that because of Hurricane Ian, this restoration qualifies for 100 percent federal funding under that emergency program, separate from the usual cost-share formula.
With full federal funding, the parking formula weighs less on this round than on the ones after it. The easements are what held it up. In a May 2025 comment on the federal docket, Lee County wrote that it had expected the Corps to award a construction contract in September 2025. Progress, it said, had been "stalled by ongoing real estate issues surrounding the extent and duration of construction easements." The county added that it was "fully prepared and committed to paying 100 percent of the nourishment costs associated with private property that does not have an easement that covers the defined life of the project and provide for public access, just as was done in 2007."
The south end has its own project too. DEP reports that State Parks is working with a consultant on an engineered design for new coastal structures to help repair the shoreline seaward of the Boca Bay Pass Club, near R-25, in 2026/2027.
Questions Worth Answering Before a Gulf-Front Closing
On a Gulf-front contract in the R10 to R24.5 reach, these are reasonable things to ask:
- Where is the parcel relative to the project's northern boundary near 17th Street and its southern end near South Beach Bar & Grille?
- What has Lee County said most recently about any renourishment assessment on Gasparilla Island, and has the commission scheduled anything?
- Will construction staging or work zones near the property be active during a planned showing period or closing date?
A Short FAQ
Is the November 2026 project confirmed? DEP's August 2026 plan calls November 2026 the expected timing and lists "2026/2027" in its project table. A contract award has not yet been announced in public reporting.
Has a Boca Grande renourishment assessment been reported as adopted? As of this fall, no adopted Boca Grande renourishment assessment has appeared in public reporting.
This post is general information, not legal, tax or financial advice. Easement terms, assessments and title questions should be confirmed with a Florida real estate attorney or the appropriate county office for your specific parcel.